This project took two years of design with Proterra (now Camber) and CapMetro. The project consisted of five sequence phases over the course of three months. Decker completed the installation of the EV charging system at CapMetro South Ops. The project included two new utility service connections, the installation of two 1.44-megawatt chargers, and a total of 48 dispensers.